──Apr 18 , 2021Construction flow of undisturbed earth taking and pressure pouring concrete pile with full protective cylinder

Full protection of JaneUndisturbed concrete cast-in-place pileIn the construction, a double-power drill with built-in spiral blades is adopted to drill down and cut soil to form pile diameter. At the same time, the soil in the simplified protection is removed, and the concrete is inserted into the steel cage after being pressed and the reinforced concrete pile is formed after the simplified protection is pulled out. Can also be used to rotary pressure steel casing (guard cylinder)), grab and other equipment take out the hole forming process of the soil inside the guard, install the steel cage after the hole forming, and fill the concrete of the pile body. It is suitable for clay soil layer, silt soil, sandy soil and high groundwater level, high confined water formation.

1,Undisturbed concrete cast-in-place pileCharacteristics of process technology

(1) No diameter expansion for hole formation, saving concrete.

(2) Do not use mud wall protection, high pile quality.

(3No mud produced, green environmental protection.

(4) high pile forming speed.

(5) The soil disturbance is small, and the construction process has little influence on the first pile and the surrounding environment, which is especially suitable for the project with high pile density.

(6No hole collapse, no neck shrinkage, high verticality, reliable quality.

2,Undisturbed concrete cast-in-place pileConstruction process flow chart

Construction process of undisturbed earth filling pile

Shanghai Qiangqiang Foundation Engineering Co., LTD. 's business covers foundation pit engineering, pile foundation engineering, land and waterFoundation treatment, slope treatment and other engineering fields. Around" Excellent technology, reliable process", construction fast "technical requirements,Is to provide customers with land, water foundation engineering technical consultation, construction services and other comprehensive solutions of the entity enterprise.Contact Number: 400-100-2850

BACK
PREV

Characteristics of reverse method in foundation pit engineering

NEXT

Protection measures for foundation pit