New technology of foundation pit engineering, effectively shorten 1/4 construction period

This project is a large furniture store invested and built by IKEA in Hefei, Anhui Province, which is a key project of the local province and city in 2020. The project is located at the intersection of Mengcheng North Road and Linquan Road, Luyang District, Hefei City. The surrounding environment is complex, with the subway station of Line 5 in the east, the subway station of Line 3 in the south, and the residential community and municipal pipeline culverts in the west. The proposed building has 4 floors above ground and 1~2 floors underground. The foundation pit depth is 7.2~15.2m and the area is about 19,000 square meters. The original foundation pit supporting scheme is: cast-in-place pile + high pressure rotary jet grouting pile water stop + composite steel support.

Hefei IKEA Store projectInvested and built by Hefei IKEA Furniture Co., LTD., the foundation pit construction unit is Shanghai Qiangqiang Foundation Engineering Co., LTD. (hereinafter referred to as"Shanghai has a strong foundation").This project has a very high requirement on the time limit.Using the traditional construction technology will be difficult to ensure the construction period. In the end,This project adoptedShanghai strong foundation new technology, will shorten the construction period1/4, meet the requirements of the construction period.  

Project Overview:

This project is IKEAHome in Hefei, Anhui provinceInvestment and construction of large home furnishingfurnitureThe mall.for2020Local provincial and municipal key projects.The project is located at the intersection of Mengcheng North Road and Linquan Road, Luyang District, Hefei, with complex surrounding environment and east5Line No. 1 subway station, south3Line No. Subway station, west according to the residential community and municipal pipeline box culvert. Proposed building on the ground4Underground floor,1~2Layer, foundation pit depth7.2~15.2m, with an area of about1.9wan㎡. The original foundation pitThe supportingSolution for:Bored piles+High pressure rotary jet grouting pile water stop+Section steel composite steel support.

A rendering of the IKEA project in Hefei

A rendering of the IKEA project in Hefei

Process improvement and optimization design:

The person in charge of the construction of this project has visited Shanghai Qiangqiang Foundation Headquarters and its ongoing projectsAfter the investigation of the construction site of the foundation pit enclosure project of the new project of Royal Palace Villa, the foundation pit supporting construction contract was signed, and the contract period was6months. Later, when Shanghai Strong Foundation made preliminary arrangements for the foundation pit construction, it was found that the traditional technology could not meet the requirements of the construction team, and it might even be delayed by about one month. Therefore, the engineering department, design department, Ministry of Commerce, material equipment Department and other departments were immediately organized to meet and discuss for many times, and finally decided to ensure the safety and construction quality of the foundation pitBelow, the enclosure structure and some supporting nodes are adoptedOur companyNew process replacement, specificmeasuresAs follows:

Sectional steel brace

Foundation pit excavation drawing

1,On the envelope structure, the envelope pile is constructed by pressure grouting pile (undisturbed earth taking pressure pouring concrete pile, Shanghai Strong foundation patent).

Compared with the traditional construction technology of cast-in-place pile, the construction of pressure cast-in-place pile has no mud discharge,Green and environmental protection, and work efficiency is fast (the piling time of a single pressure irrigation pile is1~2h, the traditional cast-in-place pile forming time is6~8h).

In this project, the construction period of enclosure pile is saved by about one month after adopting this technology.

2In terms of the support system, the original scheme uses section steel composite steel support, but some of the nodes still use reinforced concrete. As the concrete needs to be cured, the construction period will be delayed.

Design Department of our CompanyThe reinforced concrete structure is replaced by steel members specially designed for Shanghai strong foundation, so that the whole support becomes an all-steel system and the process of concrete curing is omitted.

In this project, the supporting period is saved about half a month after adopting this technology.

Panoramic view of foundation pit excavation to the first support

Panoramic view of foundation pit excavation to the first support

Panoramic view of foundation pit excavation to bottom

Panoramic view of foundation pit excavation to bottom

At present,The projectFoundation pit engineeringIt has been basically completed, and the construction period has been shortenedabout1/4And the deformation of the foundation pit is controlled in2cmWithin, the construction efficiency and quality of Shanghai strong foundation are obtainedParty A's full affirmation.

contact Us

  • No. 289, Huixian Road, Jiading District, Shanghai
  • 400-100-2850
Business contact
    Mr. Ms.
  • Type of Project:
    Pile foundation engineering Foundation pit engineering Above water foundation treatment Land foundation treatment