Supply and acceptance inspection of steel support members for foundation pit support

The hoisting of steel supporting components for foundation pit supporting is carried out according to the pre-made installation flow sequence. The numbered components transported to the designated location on the site shall enter the site at least one day in advance to meet the requirements of the hoisting schedule. The entering components shall be reasonably distributed according to the design scheme and the hoisting area.

1Foundation pit supporting steel support components supporting supply

The hoisting of steel supporting steel members of the site foundation pit support is carried out according to the pre-made installation flow sequence. The numbered members transported to the designated location of the site shall enter the site at least one day in advance to meet the requirements of the hoisting progress. The entering members shall be reasonably distributed according to the design scheme and the hoisting area.

Inform THE PROCESSING PLANT ONE WEEK IN ADVANCE ACCORDING TO THE SITE HOISTING SCHEDULE, SO THAT THE PROCESSING plant can KNOW THE arrival time OF the required components at the time of site installation. When the plan is changed, the factory shall notify the factory three days in advance. The factory shall strictly follow the component approach plan required by the site lifting progress and ship the components to the designated site on time.

Steel support for foundation pit support

2, foundation pit supporting steel support components approach acceptance inspection

After the steel support components of foundation pit support enter the site, check whether the number and serial number of the components are consistent according to the waybill. If any problem is found, explain it on the receipt in time and feed back to the processing plant so that the components can be replaced and completed.

According to the design drawing, specification and quality inspection report of the processing plant, check the quality of components and make inspection records. In order to make the unqualified components can be timely modified in the factory and ensure the construction progress, they can also be directly checked in the factory. The main inspection component dimensions, screw hole size and spacing, welding and assembling quality. Components that exceed specification errors and deform during transportation must be repaired on the ground before installation to reduce work at high altitude.

Steel support for foundation pit support

Strong foundation,24Years of industry experience,143Patents,1000+Project experience, with science and technology to make the foundation stronger, adhering to the spirit of "great country craftsman", waterDCM, waterPVDAnd other innovative technologies, to provide contractors, owners, design institute with safe water foundation treatment engineering technical consultation, construction services and other comprehensive solutions. Welcome to call for free advice:400-100-2850.

contact Us

  • No. 289, Huixian Road, Jiading District, Shanghai
  • 400-100-2850
Business contact
    Mr. Ms.
  • Type of Project:
    Pile foundation engineering Foundation pit engineering Above water foundation treatment Land foundation treatment