TRD construction method pile construction preparation

1Before site preparation, site leveling must be carried out first, and the inner side of the construction site enclosure center line must be cleared15Most of the surface and underground obstacles in the range of meters, especially the surface mixed fill soil, contain more construction waste such as stones, bricks and concrete blocks, which must be followed before constructionTRDThe construction axis of the piling machine shall be cleaned and no large stones or concrete blocks shall be ensured, and the site shall be leveled to the natural ground-0.300m(Relative elevation). The roadbed of the construction site bears loads to be able to walk100Tons of the shoe......

1· Site preparation

Before construction, the site must be leveled and the inner side of the construction site enclosure center line must be cleared15The surface and underground obstacles within the scope of meters, especially the construction waste containing more stones, bricks and concrete blocks in the surface filled soil, must be followed before constructionTRDThe method of pileThe construction axis of the machine shall be cleaned and no large stones or concrete blocks shall be ensured. The site shall be leveled to the natural ground-0.300m(relative elevation). The roadbed of the construction site bears loads to be able to walk100Ton crawler crane is standard.

2, water and electricity preparation

Comprehensive consideration of the coordination and sharing of water and power supply: according to the construction scale and equipment configuration, calculate and determine the power supply required by the site, and consider the life lighting, set up transformers and distribution systems, and comprehensively design and construct water supply sources and water supply pipe systems.

3, labor allocation

See the table for the labor of each machine. 

The picture1

4, the main mechanical equipment

According to the overall construction period requirements, combined with the actual situation of the site, the construction is planned to be equipped2Table mortar mixer,2TaiwanTRD-IIIThe pile machine cuts soil laterally to form a wall. The main mechanical equipment is provided in the table.

The picture2

Shanghai Strong Foundation Engineering Co., LTD. Business coversFoundation pit engineering Pile foundation engineering, land and water Foundation treatment , slope treatment and other engineering fields. around"Excellent technology, reliable process, fast construction" technical requirements Is to provide customers with land, water foundation engineering technical consultation, construction services and other comprehensive solutions of the entity enterprise. Contact Number:400-100-2850

contact Us

  • No. 289, Huixian Road, Jiading District, Shanghai
  • 400-100-2850
Business contact
    Mr. Ms.
  • Type of Project:
    Pile foundation engineering Foundation pit engineering Above water foundation treatment Land foundation treatment