CSM construction method of steel cage can not be below the reason

CSM construction method for the reinforcement cage can not be placed in place to prevent and deal with the measures of groove perpendicularity influence of groove perpendicularity is the first key to ensure the smooth discharge of the reinforcement cage, for the "one" type groove section of the perpendicularity must be controlled within the design requirements to ensure that the reinforcement cage smoothly into the groove; The perpendicularity of the special-shaped groove section must be controlled within the design requirements to ensure that the steel cage can be smoothly sloted.

csmThe prevention and treatment measures of reinforcement cage can not be lowered into place during construction

Effect of grooving perpendicularity

The groove perpendicularity is the first key to ensure the smooth devolution of the steel cageThe perpendicularity of the "one" type groove section must be controlled within the design requirements to ensure that the steel cage can be smoothly into the groove; The perpendicularity of the special-shaped groove section must be controlled within the design requirements to ensure that the steel cage can be smoothly sloted.

TRDContinuous wall

Steel cage production impact

The steel cage should be made on the flat production platform as a whole, and the flatness of the steel cage processing platform needs to be reviewed frequently.

Influence of steel cage hoisting

Lifting mainly controls the deformation of the steel cage and the perpendicularity of the steel cage after lifting. The control of the vertical degree of the steel cage after lifting is mainly to calculate the center of gravity of the steel cage (especially the special-shaped steel cage), the reasonable arrangement of the steel cage hanging point, so that the steel cage to maintain a good vertical degree in the process of lowering, smooth lowering.

TRDThe construction of the

Shanghai Qiangqiang Foundation Engineering Co., LTD. 's business covers foundation pit engineering, pile foundation engineering, land and waterFoundation treatment , slope treatment and other engineering fields. Around" Excellent technology, reliable process ", construction fast "technical requirements, Is to provide customers with land, water foundation engineering technical consultation, construction services and other comprehensive solutions of the entity enterprise. Contact Number:400-1002850

contact Us

  • No. 289, Huixian Road, Jiading District, Shanghai
  • 400-100-2850
Business contact
    Mr. Ms.
  • Type of Project:
    Pile foundation engineering Foundation pit engineering Above water foundation treatment Land foundation treatment