Setting of construction datum point and positioning of pull line for prestressed steel composite support

Prestressed steel composite support construction datum point setting and cable positioning requirements: Before installing enclosing purlin, the axis datum point shall be determined, and the base point of the inner side of two adjacent corners of the foundation pit shall be calculated by the total station or theodolite through the coordinate, and the plane installation and positioning shall be carried out by the method of wire hanging through the base point. The deviation of the actual installation axis must not exceed 5mm.

Requirements for setting the construction datum point and positioning the cable for prestressed steel composite support:

Before installing enclosing purlin, it is necessary to determine the axis datum point, and use the total station or theodolite to calculate and measure the base point of the inner side of the two adjacent corners of the foundation pit through coordinate calculation. Through this base point, the plane installation and positioning is carried out by the method of connecting cables. The deviation of the actual installation axis shall not exceed5mm.

Prestressed steel composite bracing

The thread used for pulling is usually string or cotton thread, diameterIn order to0.8~1.0mmAs appropriate, the site is determined by the distance of the wire; The pendant is used to set the center, the size is variable, the diameter is usually25~50mmAs appropriate, the tip of the line drop should be accurate in order to align with the center point.

A gallows is securely placed beyond the center point of the reference, string or cotton thread is hung and straightened using a tension force(The tension force should be the wire breaking force30%~0%)After positioning, mark on the triangular bracket for controlling the position of enclosing purlin installation.

The unilateral positioning line of enclosing purlin in the inner side of foundation pit should meet the basic requirement of being in a straight line, so as to ensure the uniform force of the outer envelope after applying prestress.

Prestressed steel composite bracing

Shanghai Qiangqiang Foundation Engineering Co., LTD. 's business covers foundation pit engineering, pile foundation engineering, land and waterFoundation treatment , slope treatment and other engineering fields. Around" Excellent technology, reliable process ", construction fast "technical requirements, Is to provide customers with land, water foundation engineering technical consultation, construction services and other comprehensive solutions of the entity enterprise. Contact Number:400-1002850

contact Us

  • No. 289, Huixian Road, Jiading District, Shanghai
  • 400-100-2850
Business contact
    Mr. Ms.
  • Type of Project:
    Pile foundation engineering Foundation pit engineering Above water foundation treatment Land foundation treatment